Part Lane Closure July- August 2025
PART LANE CLOSURES JULY-AUGUST 2025
FOR INTRUSIVE SITE SURVEY WORKS
We are writing to inform you that we will be undertaking site investigation survey works across the Wellesley area between 09/July until and 10/August/2025 (excluding weekends) at the following locations:
Location | Site Investigation Survey Area | Type of Survey & Traffic Management (TMs) | 2025 Survey Dates & Time | Contractor & Emergency Contact |
L1 | Alison’s Rd Phase4
(From East of Buller Roundabout to Alison’s Rd Culvert Bridge) |
CCTV Survey
Non-intrusive under Stop & Go TMs |
14/July
(Night Work 20:00-06:00hrs) |
Ultraflow
07788 297214 |
L2 | Alison’s Rd Phase6
(A325 Eastern Slip Roads and under Bridge) |
Topo/GPR Survey
Non-intrusive under Stop & Go TMs |
15-18/July
(Daytime 08:00-17:00hrs) |
Encompass
023 8069 2002
|
L3 | Louise Margaret Rd Phase1
(From Hope Grants Rd) |
Trial Holes Survey
Intrusive under Stop & Go TMs |
17-18/July
(Daytime 08:00-17:00hrs) |
Onyxgeo
07399 054246 |
L4 | Louise Margaret Rd Phase2
(From Ordnance Rd) |
Trial Holes Survey
Intrusive under Stop & Go TMs |
21-23/July
(Daytime 08:00-17:00hrs) |
Onyxgeo
07399 054246 |
L5 | Alison’s Rd Phase4
(From East of Buller Roundabout to Alison’s Rd Culvert Bridge) |
Trial Holes Survey
Intrusive under Stop & Go TMs |
28-29/July
(Daytime 08:00-17:00hrs) |
Onyxgeo
07399 054246 |
L6 | Ordnance Rd Phase1
(From Ordnance Roundabout up to Louise Margaret Rd) |
Trial Holes Survey
Intrusive under Temporary Traffic Signals TMs |
31/July
and 1,4,5/August (Daytime 08:00-17:00hrs) |
Onyxgeo
07399 054246 |
L7 | North Lane
(From Ordnance Rd to Rail Bridge Traffic Signals) |
Trial Holes Survey
Intrusive under Temporary Traffic Signals TMs |
07-10/August
(Daytime 08:00-17:00hrs) |
Onyxgeo
07399 054246 |
There will be temporary traffic management in place with part lane closures from 08:00 hours to 17:00 hours during these survey works – please see indicative map showing location areas.North Lane and Ordnance Rd surveys will have temporary ‘Traffic Signals’ in place as works progress. Whereas Louise Margaret Rd and Alison’s Rd Phase 4 will be under ‘Stop and Go’ temporary traffic management.
Access for pedestrians and cyclists will still be available via the alternative diversions on footpaths.
Please do get in touch with us if you have any questions or concerns on either 01252 351966 or email info@wellesleyhampshire.co.uk
We do apologise for the inconvenience that these works will cause, and we thank you for your patience and understanding.