Please be aware that we will be closing Hospital Hill from Monday 5th August to Sunday 25th August while we carry out the final resurfacing works to the road.

During this closure vehicle access to the Centre for Health will remain open via Queens Avenue. We have also made arrangements with the Bus Service to ensure that diversion routes, a shuttle service and signage will be in place and the impact on customers is kept to a minimum. Anyone using the bus service who is concerned about their route should get in touch with Stagecoach directly for more information www.stagecoachbus.com

Please see our map  showing the diversion routes that will be in place. Please note that Gun Hill will be open to vehicles during this closure.

We apologise for the disruption that this closure will cause but hope that by carrying out the works during the school holidays it will keep disturbance to a minimum. Once the resurfacing works have been carried out, our works to Hospital Hill will be complete.

The works have taken longer than expected mainly due to the finding of previously unrecorded underground services. We apologise for the time it has taken to complete these works and we thank you for your patience.

Our Contractors; Walker Construction, will be carrying out the works, and in the case of an emergency please contact them on 07710 077737.


Please get in touch with us if you have any questions or concerns by emailing info@wellesleyhampshire.co.uk