Development Update

The new community here at Wellesley is continuing to grow and we now have nearly 100 occupied homes within our Maida zone.

We have commenced the infrastructure works to our second zone known as Corunna, on the opposite side of Queens Avenue, and house construction will start spring 2017.

We are currently in talks with developers for our Gunhill phase of the development which sits towards Gun Hill Road. The area will feature 107 private rental homes and we hope to start works on site in spring next year.


Offsite Highway Works

We have completed the first phase of our works in Aldershot town centre along two sections of Wellington Avenue. The current Pelican crossings at the junction with Court Road and outside the High Street Car Park have been improved and turned into Toucan crossings, allowing a shared surface for both pedestrians and cyclists to safely cross at the same time.

The second stage of works to the Wellington Avenue junction with Hospital Hill will start later in 2017. These works will include widening the existing footpaths of Hospital Hill for pedestrians and cyclists to use as well as improving the crossings at the junction. These works will improve access for both pedestrians and cyclists moving between the town centre and Wellesley.


Community Room

Our Wellesley Community Rooms are nearly complete. A former military portacabin is currently being transformed into an interim community space that will be open for everyone to use. With a small hall and meeting rooms the space will be available to hire for children’s parties, meetings and more.  The facility will be open in the spring. Keep an eye on our website for further details.