Alison’s Road
Our contractor is currently carrying out utility crossing works along Alison’s Road. The road will remain open to traffic during these works, although the road may go down to one lane at certain times. These works have been extended and are expected to be completed by Friday 29 April.


We will also be carrying out drainage works which may affect parts of southern footway, these works will be completed by the end of May.

Farnborough Road
From Monday 11 April, our contractor will be carrying out utility works along part of Farnborough Road, adjacent to Pennefathers Road. To carry out this work, we will be reducing the road to one lane and will put traffic lights in place. These works have been extended due to engineering difficulties and are expected to be completed on Friday 29 April with possible traffic delays at peak times.


We do apologise for any inconvenience caused.